Week 33 – Site Progress!

Well it’s been a busy week! The gables are now finished and the chimney isn’t far off plus the roofers have felted the roof now so at least the house is covered if we have any rain yay! Annddddd the name stones are in…. So so pleased with them! Such a lovely personal touch toContinue reading “Week 33 – Site Progress!”

Front door decided..

Another decision! We have really been going round the houses…so to speak! when it comes to the front door colour, more so than style. We are pretty clear on that! The “tenby solid” is the way to go for us as we feel it is in keeping with the style of the house We wereContinue reading “Front door decided..”

Week 32 – Site Progress!

Well what a week! Much more going on and luckily the weather improved and so the brickwork could continue yay. The front gables are looking so pretty with a lovely brickwork pattern It really looks like a house now that the front gables have been finished! And also the stone cills and name stones arrived…Continue reading “Week 32 – Site Progress!”

Week 30 and 31 – Site Progress!

Not a great deal going on over the Christmas period, aside from a little more roof work on Christmas eve, and then a wait for the last of the bricks so that the gables can be finished Finally arriving in week 30, plus the ogee roof guttering came… And other than that a quiet oneContinue reading “Week 30 and 31 – Site Progress!”

Plants…trees! No we’re not avid gardeners..

Not quite there just yet with the landscaping obviously! But definitely something to think about. The front and side of the house will need to be tackled first given that there will be a house to demolish at the back! And I don’t think we had envisioned we would have this much space at theContinue reading “Plants…trees! No we’re not avid gardeners..”

Week 28 and 29 – Site Progress!

Oh the saga of waiting on materials! In this case, bricks. And the difficulty being able to pin people down for dates as well. Hopefully they will be arriving in week 30 so that the gables can be finished fingers crossed! However, at least the central section of the roof trusses have been done, andContinue reading “Week 28 and 29 – Site Progress!”

Flooring decided..

We were so undecided as to what to have in the open plan kitchen area at the back of the house for the longest time. The hallway, living room and snug at the front were a no brainer, hardwood parquet. We actually had this in our old house and loved it! So beautiful and lowContinue reading “Flooring decided..”

Double height hallway…Good decision!

Many moons ago…well it feels like that now…we made the decision to have a partial glass ceiling in the hallway, so that when walking into the house, the rooflight could be seen and really let the light in. Plus who doesn’t love a quirky glass ceiling! It was always going to be a compromise though,Continue reading “Double height hallway…Good decision!”

Week 26 and 27 – Site Progress!

We decided to group the two weeks together as week 26 was a little quiet to say the least. We were waiting until Thursday for the scaffolding to be moved up. Again they kept giving us a date and then not turning up. Obviously we know that all the trades are busy but seriously, whyContinue reading “Week 26 and 27 – Site Progress!”