Week 61 – Site Progress! First fix done plus twinkly lights…

Another milestone this week, the first fix electrics are complete and we can now focus on insulation soon, hopefully week 62! Building control paid site a visit on Wednesday and they are happy with everything so we are good to go when it comes to covering the walls and floors And our very pretty twinklyContinue reading “Week 61 – Site Progress! First fix done plus twinkly lights…”

Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..

Another week and the first fix is just about done…honestly ha! The waste pipes are now in but the plumber is missing a few bits and so hopefully he will be back in week 61…. Plus Harold has been busy with bay window cills and has almost finished the roof tiles too..just ridge tiles toContinue reading “Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..”

Week 58 – Site Progress! Plus “fiddly” lights and brick slips..

Lots going on this week! Eddie the electrician has been on site for most of it, finishing off the upstairs wiring and thermostats. The cinema room certainly took some doing…as you can see… Lots of twinkly LEDs to go in here, and doing this now will make the second fix much easier! And next weekContinue reading “Week 58 – Site Progress! Plus “fiddly” lights and brick slips..”

Week 54 – Site Progress! Stud walls, more chipboard and a huge light..

Oh my goodness..the stud walls are going up! And so far we have the utility/downstairs toilet forming eek! Our eagerness took over and we had to make a mini layout beforehand ha! Looks a little bit like a cage at the minute! And the great thing about self building is the numerous tweaking that canContinue reading “Week 54 – Site Progress! Stud walls, more chipboard and a huge light..”

Spray painting…

Eeek now we have flooring upstairs we can start to visualise and put our planned layouts into practice! Yes we have been playing around with sketchup but it always helps to actually spray paint in the actual space…I was tempted to buy some inflatable furniture too ha ha! And first off, my ensuite. Definitely bathContinue reading “Spray painting…”

Week 53 – Site Progress..chipboard and the big one…weather tight!

More chipboard this week and it’s been great, actually walking around upstairs and getting a real feel for the space! Plus a little snagging as you can imagine ha! And we are weather tight! Its a temporary door but at least we can now get the ball rolling with the self build mortgage, and theContinue reading “Week 53 – Site Progress..chipboard and the big one…weather tight!”

What a difference a year makes…

It seems only yesterday that we were getting giddy about the digger ha! And look has us now..almost weather tight and onto the interiors Cue digger pic… There has been the odd delay on the way, be it materials..or waiting for scaffolding (bug bear of mine) or measuring issues (!) but we are getting thereContinue reading “What a difference a year makes…”

Week 51 – Site Progress! Garage door, more deliveries plus decisions…

Yesssss we have a garage door! And it’s certainly a statement piece don’t you think! It is ocean blue ral 5020…the camera seems to darken the colour but you get the idea And this one is an insulated sectional remote control door…perfect for when we’re taking the dogs for walkies via the garage right! AndContinue reading “Week 51 – Site Progress! Garage door, more deliveries plus decisions…”

Week 50 – Site Progress..DIY fence and charity shop finds!

House wise, it’s been pretty quiet this week, as we are still waiting on the front door…fingers crossed that will be week 51. And so, apart from a little more window insulation and some joinery ready for the chipboard, it’s been a quiet one! However we did complete our little DIY fence project! After aContinue reading “Week 50 – Site Progress..DIY fence and charity shop finds!”

Week 49 – Site Progress..Bay windows plus fence DIY!

Another week and we now have bay windows yay! We are edging ever closer to being weather tight! Just waiting on the front door, unfortunately there’s a two week delay but hey ho. Not too long now So very excited for the peacock front door knocker! I also can’t wait to take the safety fenceContinue reading “Week 49 – Site Progress..Bay windows plus fence DIY!”