Plants…trees! No we’re not avid gardeners..

Not quite there just yet with the landscaping obviously! But definitely something to think about. The front and side of the house will need to be tackled first given that there will be a house to demolish at the back! And I don’t think we had envisioned we would have this much space at theContinue reading “Plants…trees! No we’re not avid gardeners..”

Week 28 and 29 – Site Progress!

Oh the saga of waiting on materials! In this case, bricks. And the difficulty being able to pin people down for dates as well. Hopefully they will be arriving in week 30 so that the gables can be finished fingers crossed! However, at least the central section of the roof trusses have been done, andContinue reading “Week 28 and 29 – Site Progress!”

Double height hallway…Good decision!

Many moons ago…well it feels like that now…we made the decision to have a partial glass ceiling in the hallway, so that when walking into the house, the rooflight could be seen and really let the light in. Plus who doesn’t love a quirky glass ceiling! It was always going to be a compromise though,Continue reading “Double height hallway…Good decision!”

Week 22 – Site Progress!

Another week, where does the time go!! Upstairs is really starting to take shape now, it won’t be long before the brickwork has been completed! Block and brickwork at the back of the house, eek! Next up will be the internal block work, I am so excited for that. Need to build myself up toContinue reading “Week 22 – Site Progress!”

Kitchen plans…

Very excited to have a kitchen design on paper,and it looks fabulous! Always a bonus! Originally we were going to go with something super modern, with an industrial twist. Handleless, with Copper and Slate cupboard doors but after lots of consideration we felt that we probably would want to change it in a few years,Continue reading “Kitchen plans…”

Week 20 – Site Progress!

It was all go on Tuesday this week, the scaffolding guys turned up first thing and moved all the scaffolding up a level so that the brickies can carry on with the rest of the brickwork at first floor level Its a little bit too high now for me! I’m not great with heights soContinue reading “Week 20 – Site Progress!”

Week 19 – Site Progress!

More brickwork this week ready for the scaffolding to be moved up again! The front of the house is really starting to take shape now All very exciting. Plus we have also been making decisions regarding sliding doors (last blog post) and are pretty much ready to order the stairs yay! Looking back at theContinue reading “Week 19 – Site Progress!”

Week 18 – Site Progress!

It was so refreshing to have movement on site again and less fixation on scaffolding! Week 18 saw block and brickwork at first floor level and some stone heads at the back of the house. So very pleased we have gone with the Portland Stone! It looks fabulous! Week 19 will see more brickwork aroundContinue reading “Week 18 – Site Progress!”

Week 16 – Site Progress!

Well..what can I say..it has been a VERY quiet week on site! We have been waiting for scaffolding alllllllll week, and so the brickies haven’t been able to continue to first floor. Very frustrating. Added to the fact that we kept being told that they were coming. Oh well! It came on Friday and needlessContinue reading “Week 16 – Site Progress!”

Week 15 – Site Progress!

There hasn’t been a great deal going on this week, as we are waiting for the scaffolding…Still waiting as I write this! And so the brickies have been able to pretty much complete the bay windows brickwork and are now up to first floor height! Fingers crossed the scaffolding will arrive early next week soContinue reading “Week 15 – Site Progress!”