Week 61 – Site Progress! First fix done plus twinkly lights…

Another milestone this week, the first fix electrics are complete and we can now focus on insulation soon, hopefully week 62! Building control paid site a visit on Wednesday and they are happy with everything so we are good to go when it comes to covering the walls and floors And our very pretty twinklyContinue reading “Week 61 – Site Progress! First fix done plus twinkly lights…”

Week 48 – Site Progress! We have windows AND bifolds!

What an exciting milestone this week! After a ten week wait, the windows arrived yay. As you can imagine, we were very excited. And all of them are in now, with the exception of the bay windows..it will be week 49 for those and then the tiling can begin We are so very close toContinue reading “Week 48 – Site Progress! We have windows AND bifolds!”

Week 41 – Site Progress! Plus more light deliveries and front door changes

Another week has gone by and saw the roof trusses go up ready for the porch tiles Andy set up the scaffolding ready…luckily we didn’t have to wait for the scaffolders to do this ha ha! Thankfully the salt has started to wash off the bricks..phew! It looks here as though they’ve been spray paintedContinue reading “Week 41 – Site Progress! Plus more light deliveries and front door changes”

Week 37 and 38 – Site Progress!

Another two weeks have gone by, and wow the time really does fly! Although there hasn’t been much to report from week 37, there has been more progress in week 38 luckily.  Week 37 saw some of the scaffolding come down though yay! which was exciting in itself and a great milestone! I’m pretty sureContinue reading “Week 37 and 38 – Site Progress!”

Internal doors…

This has been, for the most part, a pretty easy decision luckily…for once ha! We are actually going with Crittall sliding doors in some places, and so black was definitely the way to go when it came to the other doors. Having worked it out we only actually need 3! Due to using hidden doorsContinue reading “Internal doors…”