Week 70 – Site Progress..plus we have a front door!

Busy week plastering, and wow what a difference it makes! Also Andy has been fitting some of the borgos before plastering in our bedroom… Plus..the big one…the front door arrived! Yaassss! And wow I love it, I was so nervous that there might be something wrong with it or the colour might not be quiteContinue reading “Week 70 – Site Progress..plus we have a front door!”

Week 61 – Site Progress! First fix done plus twinkly lights…

Another milestone this week, the first fix electrics are complete and we can now focus on insulation soon, hopefully week 62! Building control paid site a visit on Wednesday and they are happy with everything so we are good to go when it comes to covering the walls and floors And our very pretty twinklyContinue reading “Week 61 – Site Progress! First fix done plus twinkly lights…”

Outdoor lights…

Something that we felt was a must when it came to the planning stages of the build, and the lighting design. And we have decided to go with up/down lights. The splay of light with these works so well in different spaces, and we will have them either side of the front door, as wellContinue reading “Outdoor lights…”

Week 57 – Site Progress..we have wires! Plus door casings,and great finds!

Busy week this week, Eddie the electrician…official name ha (!) has been on site most of the week and has pretty much done all the first fix electrics upstairs Wires..wires everywhere! And lots of them in the cinema room…we will be having twinkly LED spotlights in here… As you can see, very sparkly and we’veContinue reading “Week 57 – Site Progress..we have wires! Plus door casings,and great finds!”

Acoustic panelling..

As we are underway with the stud walls, and rooms are starting to take shape, we can give a little more thought to the hidden door in the tiki bar! If you have seen on our Instagram, we will be having a coat cupboard in this room,and as it is just off from the hallwayContinue reading “Acoustic panelling..”

Spray painting…

Eeek now we have flooring upstairs we can start to visualise and put our planned layouts into practice! Yes we have been playing around with sketchup but it always helps to actually spray paint in the actual space…I was tempted to buy some inflatable furniture too ha ha! And first off, my ensuite. Definitely bathContinue reading “Spray painting…”

Week 53 – Site Progress..chipboard and the big one…weather tight!

More chipboard this week and it’s been great, actually walking around upstairs and getting a real feel for the space! Plus a little snagging as you can imagine ha! And we are weather tight! Its a temporary door but at least we can now get the ball rolling with the self build mortgage, and theContinue reading “Week 53 – Site Progress..chipboard and the big one…weather tight!”

Double height decisions…

As you may have picked up on in our previous posts, we are keen to really make the hallway/landing a focal point and show off interesting materials and height differences And so, as well as having a central staircase with a concrete stair, wooden treads and a black metal balustrade we have decided to stopContinue reading “Double height decisions…”

Week 51 – Site Progress! Garage door, more deliveries plus decisions…

Yesssss we have a garage door! And it’s certainly a statement piece don’t you think! It is ocean blue ral 5020…the camera seems to darken the colour but you get the idea And this one is an insulated sectional remote control door…perfect for when we’re taking the dogs for walkies via the garage right! AndContinue reading “Week 51 – Site Progress! Garage door, more deliveries plus decisions…”

Week 48 – Site Progress! We have windows AND bifolds!

What an exciting milestone this week! After a ten week wait, the windows arrived yay. As you can imagine, we were very excited. And all of them are in now, with the exception of the bay windows..it will be week 49 for those and then the tiling can begin We are so very close toContinue reading “Week 48 – Site Progress! We have windows AND bifolds!”