Week 57 – Site Progress..we have wires! Plus door casings,and great finds!

Busy week this week, Eddie the electrician…official name ha (!) has been on site most of the week and has pretty much done all the first fix electrics upstairs Wires..wires everywhere! And lots of them in the cinema room…we will be having twinkly LED spotlights in here… As you can see, very sparkly and we’veContinue reading “Week 57 – Site Progress..we have wires! Plus door casings,and great finds!”

Acoustic panelling..

As we are underway with the stud walls, and rooms are starting to take shape, we can give a little more thought to the hidden door in the tiki bar! If you have seen on our Instagram, we will be having a coat cupboard in this room,and as it is just off from the hallwayContinue reading “Acoustic panelling..”

Spray painting…

Eeek now we have flooring upstairs we can start to visualise and put our planned layouts into practice! Yes we have been playing around with sketchup but it always helps to actually spray paint in the actual space…I was tempted to buy some inflatable furniture too ha ha! And first off, my ensuite. Definitely bathContinue reading “Spray painting…”

Week 53 – Site Progress..chipboard and the big one…weather tight!

More chipboard this week and it’s been great, actually walking around upstairs and getting a real feel for the space! Plus a little snagging as you can imagine ha! And we are weather tight! Its a temporary door but at least we can now get the ball rolling with the self build mortgage, and theContinue reading “Week 53 – Site Progress..chipboard and the big one…weather tight!”

Double height decisions…

As you may have picked up on in our previous posts, we are keen to really make the hallway/landing a focal point and show off interesting materials and height differences And so, as well as having a central staircase with a concrete stair, wooden treads and a black metal balustrade we have decided to stopContinue reading “Double height decisions…”

Week 51 – Site Progress! Garage door, more deliveries plus decisions…

Yesssss we have a garage door! And it’s certainly a statement piece don’t you think! It is ocean blue ral 5020…the camera seems to darken the colour but you get the idea And this one is an insulated sectional remote control door…perfect for when we’re taking the dogs for walkies via the garage right! AndContinue reading “Week 51 – Site Progress! Garage door, more deliveries plus decisions…”

Week 48 – Site Progress! We have windows AND bifolds!

What an exciting milestone this week! After a ten week wait, the windows arrived yay. As you can imagine, we were very excited. And all of them are in now, with the exception of the bay windows..it will be week 49 for those and then the tiling can begin We are so very close toContinue reading “Week 48 – Site Progress! We have windows AND bifolds!”

Week 41 – Site Progress! Plus more light deliveries and front door changes

Another week has gone by and saw the roof trusses go up ready for the porch tiles Andy set up the scaffolding ready…luckily we didn’t have to wait for the scaffolders to do this ha ha! Thankfully the salt has started to wash off the bricks..phew! It looks here as though they’ve been spray paintedContinue reading “Week 41 – Site Progress! Plus more light deliveries and front door changes”

Week 39 and 40 – Site Progress!

Not a whole lot to report, simply because the windows and doors won’t be arriving for another month or so, which means there is no rush really! The garage roof trusses are up, and we ordered our garage door too eek! I didn’t realise I’d get excited over a garage door…and I don’t think AndyContinue reading “Week 39 and 40 – Site Progress!”

Peacock mural plus a hidden door…

As we are getting ever closer to the interiors, we have been giving a little more thought to our bedroom. Having already decided on colours, namely pale greens and pinks, we had been toying with the idea of a feature wall but perhaps one in the shape of a mural As you can imagine, somethingContinue reading “Peacock mural plus a hidden door…”