Week 55 – Site Progress..another stud wall plus ready for first fix!

A pretty quiet one but we do have another stud wall and the first fix on the horizon! This one is the Jack and Jill ensuite upstairs for the guest bedroom and cinema room It’s pretty cool being able to play around with room sizes. In this case we made the window central to theContinue reading “Week 55 – Site Progress..another stud wall plus ready for first fix!”

Week 54 – Site Progress! Stud walls, more chipboard and a huge light..

Oh my goodness..the stud walls are going up! And so far we have the utility/downstairs toilet forming eek! Our eagerness took over and we had to make a mini layout beforehand ha! Looks a little bit like a cage at the minute! And the great thing about self building is the numerous tweaking that canContinue reading “Week 54 – Site Progress! Stud walls, more chipboard and a huge light..”

Week 53 – Site Progress..chipboard and the big one…weather tight!

More chipboard this week and it’s been great, actually walking around upstairs and getting a real feel for the space! Plus a little snagging as you can imagine ha! And we are weather tight! Its a temporary door but at least we can now get the ball rolling with the self build mortgage, and theContinue reading “Week 53 – Site Progress..chipboard and the big one…weather tight!”

What a difference a year makes…

It seems only yesterday that we were getting giddy about the digger ha! And look has us now..almost weather tight and onto the interiors Cue digger pic… There has been the odd delay on the way, be it materials..or waiting for scaffolding (bug bear of mine) or measuring issues (!) but we are getting thereContinue reading “What a difference a year makes…”

Week 30 and 31 – Site Progress!

Not a great deal going on over the Christmas period, aside from a little more roof work on Christmas eve, and then a wait for the last of the bricks so that the gables can be finished Finally arriving in week 30, plus the ogee roof guttering came… And other than that a quiet oneContinue reading “Week 30 and 31 – Site Progress!”

Week 28 and 29 – Site Progress!

Oh the saga of waiting on materials! In this case, bricks. And the difficulty being able to pin people down for dates as well. Hopefully they will be arriving in week 30 so that the gables can be finished fingers crossed! However, at least the central section of the roof trusses have been done, andContinue reading “Week 28 and 29 – Site Progress!”

Flooring decided..

We were so undecided as to what to have in the open plan kitchen area at the back of the house for the longest time. The hallway, living room and snug at the front were a no brainer, hardwood parquet. We actually had this in our old house and loved it! So beautiful and lowContinue reading “Flooring decided..”

Kitchen plans…

Very excited to have a kitchen design on paper,and it looks fabulous! Always a bonus! Originally we were going to go with something super modern, with an industrial twist. Handleless, with Copper and Slate cupboard doors but after lots of consideration we felt that we probably would want to change it in a few years,Continue reading “Kitchen plans…”

The stairs are ordered!

So excited! It really feels like a big milestone when you are almost ready to have the stairs installed eek. If you haven’t seen our past instagram posts we are going for a precast concrete central staircase. And so the stairs will be made off site and then craned into place We have now signedContinue reading “The stairs are ordered!”

Week 19 – Site Progress!

More brickwork this week ready for the scaffolding to be moved up again! The front of the house is really starting to take shape now All very exciting. Plus we have also been making decisions regarding sliding doors (last blog post) and are pretty much ready to order the stairs yay! Looking back at theContinue reading “Week 19 – Site Progress!”