Week 28 and 29 – Site Progress!

Oh the saga of waiting on materials! In this case, bricks. And the difficulty being able to pin people down for dates as well. Hopefully they will be arriving in week 30 so that the gables can be finished fingers crossed! However, at least the central section of the roof trusses have been done, andContinue reading “Week 28 and 29 – Site Progress!”

Week 26 and 27 – Site Progress!

We decided to group the two weeks together as week 26 was a little quiet to say the least. We were waiting until Thursday for the scaffolding to be moved up. Again they kept giving us a date and then not turning up. Obviously we know that all the trades are busy but seriously, whyContinue reading “Week 26 and 27 – Site Progress!”

Week 19 – Site Progress!

More brickwork this week ready for the scaffolding to be moved up again! The front of the house is really starting to take shape now All very exciting. Plus we have also been making decisions regarding sliding doors (last blog post) and are pretty much ready to order the stairs yay! Looking back at theContinue reading “Week 19 – Site Progress!”

Week 17 – Site Progress!

Well…we were expecting the rest of the scaffolding on Monday so that brickwork could continue however they didn’t turn up until Thursday and so we lost another week of brickwork! But onwards and upwards as they say, blockwork will continue in week 18 up to first floor yay!! And we can now see just howContinue reading “Week 17 – Site Progress!”

Week 16 – Site Progress!

Well..what can I say..it has been a VERY quiet week on site! We have been waiting for scaffolding alllllllll week, and so the brickies haven’t been able to continue to first floor. Very frustrating. Added to the fact that we kept being told that they were coming. Oh well! It came on Friday and needlessContinue reading “Week 16 – Site Progress!”

Week 15 – Site Progress!

There hasn’t been a great deal going on this week, as we are waiting for the scaffolding…Still waiting as I write this! And so the brickies have been able to pretty much complete the bay windows brickwork and are now up to first floor height! Fingers crossed the scaffolding will arrive early next week soContinue reading “Week 15 – Site Progress!”

Week 14 – Site Progress!

Another busy week apart from some rain…standard British weather! We now have steel though eek! Very exciting. Check out the mechanism to put the steel in place! That looked like it really took some leverage and energy! Plus a wood delivery! Lots of joists are in place now…check out our view from the current house…Continue reading “Week 14 – Site Progress!”

Giveaway Alert!

We are blown away by the renders @envisionhomedesigns have very kindly gifted to us, using our 2D plans. Sunset render above…love! https://www.instagram.com/envisionhomedesigns/ Such a fabulous way to really visualise your project! And so lifelike! If you would like to be in with a chance to win the same front façade for your project check outContinue reading “Giveaway Alert!”

Week 13 – Site progress!

More blockwork this week with internal walls and actual doorways! Eek! Plus the fireplace has been finished as well, and it is beautiful. As we have no doubt mentioned numerous times! We are leaving it exactly like this, no painting of the concrete lintel. It looks so good as is! Plus the peacocks decided toContinue reading “Week 13 – Site progress!”

Week 12 – Site Progress! Plus the first 3 months timelapse!!

More blockwork this week, going up to first floor level, it is deceptively high! Our ceiling height is 2.415 which is a little higher than standard but still…and obviously the floor levels will differ to now, it does feel high though! And I’m not complaining Love love love our exposed brick wall! We are soContinue reading “Week 12 – Site Progress! Plus the first 3 months timelapse!!”