Weeks 78 and 79 – More flooring plus guest bedroom architrave!

Week 78 was a little quiet, given that the electrician has been held up on other jobs. So, just some more flooring and light deliveries! These ones were out of stock for a while, but luckily, they were available again, phew! And they are the plaster lights mentioned in previous posts..we had only ordered oneContinue reading “Weeks 78 and 79 – More flooring plus guest bedroom architrave!”

Weeks 75 and 76 – Lots of flooring plus more painting and the first of the lights!

Lots more painting this last couple of weeks! We are almost there now, I’m so over painting ha! It’s just so messy, I can’t wait to have a good old sweep up and a tidy..and put away the paint brushes…and the sprayer! We actually did the walls of my dressing room and our bedroom withContinue reading “Weeks 75 and 76 – Lots of flooring plus more painting and the first of the lights!”

Week 70 – Site Progress..plus we have a front door!

Busy week plastering, and wow what a difference it makes! Also Andy has been fitting some of the borgos before plastering in our bedroom… Plus..the big one…the front door arrived! Yaassss! And wow I love it, I was so nervous that there might be something wrong with it or the colour might not be quiteContinue reading “Week 70 – Site Progress..plus we have a front door!”

Week 69 – Site Progress! More plasterboard plus floor decisions and a paint sprayer…

Eeekkkk lots more plasterboard this week! And the vaulted ceiling areas are looking fabulous! Wow it is really starting to look like a house. It’s so strange when you live pretty much on “site” and it develops into a home rather than a build project ha! And as you can see, we are a littleContinue reading “Week 69 – Site Progress! More plasterboard plus floor decisions and a paint sprayer…”

Week 61 – Site Progress! First fix done plus twinkly lights…

Another milestone this week, the first fix electrics are complete and we can now focus on insulation soon, hopefully week 62! Building control paid site a visit on Wednesday and they are happy with everything so we are good to go when it comes to covering the walls and floors And our very pretty twinklyContinue reading “Week 61 – Site Progress! First fix done plus twinkly lights…”

Outdoor lights…

Something that we felt was a must when it came to the planning stages of the build, and the lighting design. And we have decided to go with up/down lights. The splay of light with these works so well in different spaces, and we will have them either side of the front door, as wellContinue reading “Outdoor lights…”

Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..

Another week and the first fix is just about done…honestly ha! The waste pipes are now in but the plumber is missing a few bits and so hopefully he will be back in week 61…. Plus Harold has been busy with bay window cills and has almost finished the roof tiles too..just ridge tiles toContinue reading “Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..”

Week 53 – Site Progress..chipboard and the big one…weather tight!

More chipboard this week and it’s been great, actually walking around upstairs and getting a real feel for the space! Plus a little snagging as you can imagine ha! And we are weather tight! Its a temporary door but at least we can now get the ball rolling with the self build mortgage, and theContinue reading “Week 53 – Site Progress..chipboard and the big one…weather tight!”

Week 51 – Site Progress! Garage door, more deliveries plus decisions…

Yesssss we have a garage door! And it’s certainly a statement piece don’t you think! It is ocean blue ral 5020…the camera seems to darken the colour but you get the idea And this one is an insulated sectional remote control door…perfect for when we’re taking the dogs for walkies via the garage right! AndContinue reading “Week 51 – Site Progress! Garage door, more deliveries plus decisions…”

Week 48 – Site Progress! We have windows AND bifolds!

What an exciting milestone this week! After a ten week wait, the windows arrived yay. As you can imagine, we were very excited. And all of them are in now, with the exception of the bay windows..it will be week 49 for those and then the tiling can begin We are so very close toContinue reading “Week 48 – Site Progress! We have windows AND bifolds!”