Week 41 – Site Progress! Plus more light deliveries and front door changes

Another week has gone by and saw the roof trusses go up ready for the porch tiles Andy set up the scaffolding ready…luckily we didn’t have to wait for the scaffolders to do this ha ha! Thankfully the salt has started to wash off the bricks..phew! It looks here as though they’ve been spray paintedContinue reading “Week 41 – Site Progress! Plus more light deliveries and front door changes”

Light design!

SO when I began writing this post we WERE going to “freestyle” the lighting design and basically do it all ourselves and hope for the best essentially! I would say we are pretty creative and have a relatively good idea of what we like and don’t like. However the lights have been a bit ofContinue reading “Light design!”

Week 35 – Site Progress!

Yes! A productive week after a very quiet week 34! The roof tilers came on Wednesday and laid out all the tiles ready to put them in place on Friday And they had the best contraption! A tile conveyer belt. I want one! Or at least to use to send brews up ha! And Dave,Continue reading “Week 35 – Site Progress!”

SketchUp!

Wow what a revelation! This is such a fabulous way to visualise your home and get an idea of scale. It takes a little bit of patience and practice but it is so worth it..and its free! If you don’t go with the pro options that is, but this is what we have managed toContinue reading “SketchUp!”

Flooring decided..

We were so undecided as to what to have in the open plan kitchen area at the back of the house for the longest time. The hallway, living room and snug at the front were a no brainer, hardwood parquet. We actually had this in our old house and loved it! So beautiful and lowContinue reading “Flooring decided..”

Double height hallway…Good decision!

Many moons ago…well it feels like that now…we made the decision to have a partial glass ceiling in the hallway, so that when walking into the house, the rooflight could be seen and really let the light in. Plus who doesn’t love a quirky glass ceiling! It was always going to be a compromise though,Continue reading “Double height hallway…Good decision!”

Week 26 and 27 – Site Progress!

We decided to group the two weeks together as week 26 was a little quiet to say the least. We were waiting until Thursday for the scaffolding to be moved up. Again they kept giving us a date and then not turning up. Obviously we know that all the trades are busy but seriously, whyContinue reading “Week 26 and 27 – Site Progress!”

Week 22 – Site Progress!

Another week, where does the time go!! Upstairs is really starting to take shape now, it won’t be long before the brickwork has been completed! Block and brickwork at the back of the house, eek! Next up will be the internal block work, I am so excited for that. Need to build myself up toContinue reading “Week 22 – Site Progress!”

The stairs are ordered!

So excited! It really feels like a big milestone when you are almost ready to have the stairs installed eek. If you haven’t seen our past instagram posts we are going for a precast concrete central staircase. And so the stairs will be made off site and then craned into place We have now signedContinue reading “The stairs are ordered!”

Week 19 – Site Progress!

More brickwork this week ready for the scaffolding to be moved up again! The front of the house is really starting to take shape now All very exciting. Plus we have also been making decisions regarding sliding doors (last blog post) and are pretty much ready to order the stairs yay! Looking back at theContinue reading “Week 19 – Site Progress!”