Week 86 – Second fix almost complete plus Crittall samples!

Wow, another milestone…we have light upstairs! And Eddie, the electrician, is almost done! Maybe just a few more days than we are good to go. And the cinema room really is taking shape; these small diamond spotlights are SO twinkly!! And the lightsaber wall lights finish it off a treat! Great advice from Claire atContinue reading “Week 86 – Second fix almost complete plus Crittall samples!”

Week 83 – Microcement! Plus underfloor heating, flooring and more samples..

Happy new year!! We’ve certainly had a busy one, and are edging closer to the finishing touches! And, I thought we were pretty much done with light decisions…no such luck ha! We actually recently changed our minds when it came to the living room ceiling light…we were going to go with a large vertigo pendantContinue reading “Week 83 – Microcement! Plus underfloor heating, flooring and more samples..”

Week 77..we have a floor!!

Another week and the first of the flooring has been laid, in the soon to be tiki bar! We decided to measure from the centre of the house, as the same floor will run through the whole of the ground floor. And as luck would have it, our house is so symmetrical, the herringbone patternContinue reading “Week 77..we have a floor!!”

Weeks 75 and 76 – Lots of flooring plus more painting and the first of the lights!

Lots more painting this last couple of weeks! We are almost there now, I’m so over painting ha! It’s just so messy, I can’t wait to have a good old sweep up and a tidy..and put away the paint brushes…and the sprayer! We actually did the walls of my dressing room and our bedroom withContinue reading “Weeks 75 and 76 – Lots of flooring plus more painting and the first of the lights!”

Week 70 – Site Progress..plus we have a front door!

Busy week plastering, and wow what a difference it makes! Also Andy has been fitting some of the borgos before plastering in our bedroom… Plus..the big one…the front door arrived! Yaassss! And wow I love it, I was so nervous that there might be something wrong with it or the colour might not be quiteContinue reading “Week 70 – Site Progress..plus we have a front door!”

Kitchen decisions..

So! We have changed our minds numerous times when it comes to the kitchen and the utility..if you have seen our Instagram over the past year you will see the odd “decision made” post ha! From Wren to Howdens to diy kitchens…we couldn’t quite decide on something that was “us”. We began with copper, handlelessContinue reading “Kitchen decisions..”

Week 61 – Site Progress! First fix done plus twinkly lights…

Another milestone this week, the first fix electrics are complete and we can now focus on insulation soon, hopefully week 62! Building control paid site a visit on Wednesday and they are happy with everything so we are good to go when it comes to covering the walls and floors And our very pretty twinklyContinue reading “Week 61 – Site Progress! First fix done plus twinkly lights…”

Outdoor lights…

Something that we felt was a must when it came to the planning stages of the build, and the lighting design. And we have decided to go with up/down lights. The splay of light with these works so well in different spaces, and we will have them either side of the front door, as wellContinue reading “Outdoor lights…”

Picket fences and brick walls…

So…we have been giving a little more thought to the landscaping, its still way off yet but I can dream ha! Once the drainage has been sorted, we can at least level out the front and side of the house but we probably won’t get really stuck in until the cottage we are living inContinue reading “Picket fences and brick walls…”

Double height decisions…

As you may have picked up on in our previous posts, we are keen to really make the hallway/landing a focal point and show off interesting materials and height differences And so, as well as having a central staircase with a concrete stair, wooden treads and a black metal balustrade we have decided to stopContinue reading “Double height decisions…”