House update!!

Well, we are getting there with the kitchen and flooring. But for the last couple of months, our focus has been on the ensuites, hence the lack of updates! Excitingly, they will feature on a channel 5 TV programme called Dream Kitchens and Bathrooms! Which means we haven’t been able to share any updates, unfortunately,Continue reading “House update!!”

Week 87 – We have a kitchen!

Yaassssss! We do indeed have a kitchen and utility! Woop! Andy picked them up on Friday and what a road trip. A 5 hour round trip in total, but it’s all home now and ready for fitting! And definitely one to start in week 88! It’s really filled the back room. I didn’t think we’dContinue reading “Week 87 – We have a kitchen!”

Week 84 – More underfloor..this time upstairs!

A busy week for us with underfloor installation and touch-up paint jobs! It looks so much tidier now that the overlay panels are down!! Unlike downstairs in which the underfloor piping was stapled down and a screed applied, the upstairs is somewhat quicker, using the panels and positioning the pipes. All in it took aboutContinue reading “Week 84 – More underfloor..this time upstairs!”

Week 83 – Microcement! Plus underfloor heating, flooring and more samples..

Happy new year!! We’ve certainly had a busy one, and are edging closer to the finishing touches! And, I thought we were pretty much done with light decisions…no such luck ha! We actually recently changed our minds when it came to the living room ceiling light…we were going to go with a large vertigo pendantContinue reading “Week 83 – Microcement! Plus underfloor heating, flooring and more samples..”

Week 81 and 82 – Happy Christmas!

Well, we certainly had a busy couple of weeks with flooring and lights! Eddie, the electrician, set up some of the circuits, and as I drove up to the house from work, it was so strange seeing light and so exciting!! Plus we have been able to take the scaffolding down, now that updown lightsContinue reading “Week 81 and 82 – Happy Christmas!”

Week 77..we have a floor!!

Another week and the first of the flooring has been laid, in the soon to be tiki bar! We decided to measure from the centre of the house, as the same floor will run through the whole of the ground floor. And as luck would have it, our house is so symmetrical, the herringbone patternContinue reading “Week 77..we have a floor!!”

Weeks 75 and 76 – Lots of flooring plus more painting and the first of the lights!

Lots more painting this last couple of weeks! We are almost there now, I’m so over painting ha! It’s just so messy, I can’t wait to have a good old sweep up and a tidy..and put away the paint brushes…and the sprayer! We actually did the walls of my dressing room and our bedroom withContinue reading “Weeks 75 and 76 – Lots of flooring plus more painting and the first of the lights!”

Week 61 – Site Progress! First fix done plus twinkly lights…

Another milestone this week, the first fix electrics are complete and we can now focus on insulation soon, hopefully week 62! Building control paid site a visit on Wednesday and they are happy with everything so we are good to go when it comes to covering the walls and floors And our very pretty twinklyContinue reading “Week 61 – Site Progress! First fix done plus twinkly lights…”

Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..

Another week and the first fix is just about done…honestly ha! The waste pipes are now in but the plumber is missing a few bits and so hopefully he will be back in week 61…. Plus Harold has been busy with bay window cills and has almost finished the roof tiles too..just ridge tiles toContinue reading “Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..”

Week 58 – Site Progress! Plus “fiddly” lights and brick slips..

Lots going on this week! Eddie the electrician has been on site for most of it, finishing off the upstairs wiring and thermostats. The cinema room certainly took some doing…as you can see… Lots of twinkly LEDs to go in here, and doing this now will make the second fix much easier! And next weekContinue reading “Week 58 – Site Progress! Plus “fiddly” lights and brick slips..”