Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..

Another week and the first fix is just about done…honestly ha! The waste pipes are now in but the plumber is missing a few bits and so hopefully he will be back in week 61…. Plus Harold has been busy with bay window cills and has almost finished the roof tiles too..just ridge tiles toContinue reading “Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..”

Week 58 – Site Progress! Plus “fiddly” lights and brick slips..

Lots going on this week! Eddie the electrician has been on site for most of it, finishing off the upstairs wiring and thermostats. The cinema room certainly took some doing…as you can see… Lots of twinkly LEDs to go in here, and doing this now will make the second fix much easier! And next weekContinue reading “Week 58 – Site Progress! Plus “fiddly” lights and brick slips..”

Week 57 – Site Progress..we have wires! Plus door casings,and great finds!

Busy week this week, Eddie the electrician…official name ha (!) has been on site most of the week and has pretty much done all the first fix electrics upstairs Wires..wires everywhere! And lots of them in the cinema room…we will be having twinkly LED spotlights in here… As you can see, very sparkly and we’veContinue reading “Week 57 – Site Progress..we have wires! Plus door casings,and great finds!”

Week 56 – Site Progress..first fix electrics and more stud walls

More progress this week! Andy has been assigned some plumbing tasks and so he made a start on those…cue plumbing related items laid out all pretty in the house ha ha! And he invested in a new drill, and special drill bit making drilling the plumbing holes much easier! Needless to say he’s very happyContinue reading “Week 56 – Site Progress..first fix electrics and more stud walls”

Week 55 – Site Progress..another stud wall plus ready for first fix!

A pretty quiet one but we do have another stud wall and the first fix on the horizon! This one is the Jack and Jill ensuite upstairs for the guest bedroom and cinema room It’s pretty cool being able to play around with room sizes. In this case we made the window central to theContinue reading “Week 55 – Site Progress..another stud wall plus ready for first fix!”

Week 54 – Site Progress! Stud walls, more chipboard and a huge light..

Oh my goodness..the stud walls are going up! And so far we have the utility/downstairs toilet forming eek! Our eagerness took over and we had to make a mini layout beforehand ha! Looks a little bit like a cage at the minute! And the great thing about self building is the numerous tweaking that canContinue reading “Week 54 – Site Progress! Stud walls, more chipboard and a huge light..”

Week 51 – Site Progress! Garage door, more deliveries plus decisions…

Yesssss we have a garage door! And it’s certainly a statement piece don’t you think! It is ocean blue ral 5020…the camera seems to darken the colour but you get the idea And this one is an insulated sectional remote control door…perfect for when we’re taking the dogs for walkies via the garage right! AndContinue reading “Week 51 – Site Progress! Garage door, more deliveries plus decisions…”

Pendant lights…

If you are following our Instagram you might know that we are having a double height space in our hallway and, essentially, really showing off the space and the look of the stairs The stairs, might I add, are concrete and will have wooden treads, together with a black metal balustrade Plus we also haveContinue reading “Pendant lights…”

Ensuite plans!

For the most part, I have pretty much decided both layout and colours for my ensuite…yay go me ha ha! I’ve been keen to incorporate a touch of terrazzo in the design and love this one from Terrazzo tiles I was originally going to go for a white patterned terrazzo but I’ve decided to goContinue reading “Ensuite plans!”

Week 44 – Site Progress plus more lights!

Not a whole lot going on this week, we were hopeful that the garage door would be fitted but that wasn’t to be….well not entirely anyway! The fitters set it up however the company had measured incorrectly by around 300mm and so either the whole door will need to be made again or another panelContinue reading “Week 44 – Site Progress plus more lights!”