Week 33 – Site Progress!

Well it’s been a busy week! The gables are now finished and the chimney isn’t far off plus the roofers have felted the roof now so at least the house is covered if we have any rain yay! Annddddd the name stones are in…. So so pleased with them! Such a lovely personal touch toContinue reading “Week 33 – Site Progress!”

Week 30 and 31 – Site Progress!

Not a great deal going on over the Christmas period, aside from a little more roof work on Christmas eve, and then a wait for the last of the bricks so that the gables can be finished Finally arriving in week 30, plus the ogee roof guttering came… And other than that a quiet oneContinue reading “Week 30 and 31 – Site Progress!”

Plants…trees! No we’re not avid gardeners..

Not quite there just yet with the landscaping obviously! But definitely something to think about. The front and side of the house will need to be tackled first given that there will be a house to demolish at the back! And I don’t think we had envisioned we would have this much space at theContinue reading “Plants…trees! No we’re not avid gardeners..”

Week 28 and 29 – Site Progress!

Oh the saga of waiting on materials! In this case, bricks. And the difficulty being able to pin people down for dates as well. Hopefully they will be arriving in week 30 so that the gables can be finished fingers crossed! However, at least the central section of the roof trusses have been done, andContinue reading “Week 28 and 29 – Site Progress!”

Flooring decided..

We were so undecided as to what to have in the open plan kitchen area at the back of the house for the longest time. The hallway, living room and snug at the front were a no brainer, hardwood parquet. We actually had this in our old house and loved it! So beautiful and lowContinue reading “Flooring decided..”

Double height hallway…Good decision!

Many moons ago…well it feels like that now…we made the decision to have a partial glass ceiling in the hallway, so that when walking into the house, the rooflight could be seen and really let the light in. Plus who doesn’t love a quirky glass ceiling! It was always going to be a compromise though,Continue reading “Double height hallway…Good decision!”

Week 26 and 27 – Site Progress!

We decided to group the two weeks together as week 26 was a little quiet to say the least. We were waiting until Thursday for the scaffolding to be moved up. Again they kept giving us a date and then not turning up. Obviously we know that all the trades are busy but seriously, whyContinue reading “Week 26 and 27 – Site Progress!”

Week 24! (6 months) Site Progress!

Oh my goodness, we are now at the 6 month mark! Andy was so very excited to make the 6 month timelapse. Amazing how much can happen in 6 months and to catch it all on camera as well! This week the brickies were only here at the beginning of the week as there wasn’tContinue reading “Week 24! (6 months) Site Progress!”

Week 22 – Site Progress!

Another week, where does the time go!! Upstairs is really starting to take shape now, it won’t be long before the brickwork has been completed! Block and brickwork at the back of the house, eek! Next up will be the internal block work, I am so excited for that. Need to build myself up toContinue reading “Week 22 – Site Progress!”

Kitchen plans…

Very excited to have a kitchen design on paper,and it looks fabulous! Always a bonus! Originally we were going to go with something super modern, with an industrial twist. Handleless, with Copper and Slate cupboard doors but after lots of consideration we felt that we probably would want to change it in a few years,Continue reading “Kitchen plans…”