Week 73 – More paint spraying, white paint samples..plus go big or go home….!

And so, this week we finished all the undercoat painting, and we used Express Coat by Valspar from B&Q. This one can be used on fresh plaster and doesn’t need watering down, always a bonus! The downstairs took around 4 hours for 110 metre squared which isn’t bad going at all! I do love thisContinue reading “Week 73 – More paint spraying, white paint samples..plus go big or go home….!”

Week 72 – The paint spraying has begun..plus staining wood and another light!

It is so strange to be at a stage where it is down to us and the progress is actually ours to control…mu ha ha! And it is quite simply, based on how proactive or lazy we are feeling on any given week ha! And so this week Andy’s been sanding more of the unfinishedContinue reading “Week 72 – The paint spraying has begun..plus staining wood and another light!”

Week 71 – Site Progress!

Annnnddddd the plastering is now finished woop!! All done by Friday and now it’s just drying out before we start painting next weekend…eek! The plasterer said we could probably leave it just a few days before making a start on the painting, but we think we’ll wait…patience is key ha! Love love love the landingContinue reading “Week 71 – Site Progress!”