Something I’ve been SO excited to put together, is my dressing room! Who wouldn’t?! And I decided to go with the Ikea PAX system. If you’re not familiar with this, it is a modular system, with lots of different internal options, and can be designed to suit your requirements. It can be a lot ofContinue reading “Ikea hack! The PAX system…”
Tag Archives: photography
Week 87 – We have a kitchen!
Yaassssss! We do indeed have a kitchen and utility! Woop! Andy picked them up on Friday and what a road trip. A 5 hour round trip in total, but it’s all home now and ready for fitting! And definitely one to start in week 88! It’s really filled the back room. I didn’t think we’dContinue reading “Week 87 – We have a kitchen!”
Week 86 – Second fix almost complete plus Crittall samples!
Wow, another milestone…we have light upstairs! And Eddie, the electrician, is almost done! Maybe just a few more days than we are good to go. And the cinema room really is taking shape; these small diamond spotlights are SO twinkly!! And the lightsaber wall lights finish it off a treat! Great advice from Claire atContinue reading “Week 86 – Second fix almost complete plus Crittall samples!”
Week 84 – More underfloor..this time upstairs!
A busy week for us with underfloor installation and touch-up paint jobs! It looks so much tidier now that the overlay panels are down!! Unlike downstairs in which the underfloor piping was stapled down and a screed applied, the upstairs is somewhat quicker, using the panels and positioning the pipes. All in it took aboutContinue reading “Week 84 – More underfloor..this time upstairs!”
Week 81 and 82 – Happy Christmas!
Well, we certainly had a busy couple of weeks with flooring and lights! Eddie, the electrician, set up some of the circuits, and as I drove up to the house from work, it was so strange seeing light and so exciting!! Plus we have been able to take the scaffolding down, now that updown lightsContinue reading “Week 81 and 82 – Happy Christmas!”
Weeks 78 and 79 – More flooring plus guest bedroom architrave!
Week 78 was a little quiet, given that the electrician has been held up on other jobs. So, just some more flooring and light deliveries! These ones were out of stock for a while, but luckily, they were available again, phew! And they are the plaster lights mentioned in previous posts..we had only ordered oneContinue reading “Weeks 78 and 79 – More flooring plus guest bedroom architrave!”
Week 77..we have a floor!!
Another week and the first of the flooring has been laid, in the soon to be tiki bar! We decided to measure from the centre of the house, as the same floor will run through the whole of the ground floor. And as luck would have it, our house is so symmetrical, the herringbone patternContinue reading “Week 77..we have a floor!!”
Week 74 – Let there be colour! Plus we can officially have electricity!
The 3 phase electric meter is now good to go and we can ask the electrician to come back..more importantly, yay!! Apparently there aren’t a lot of installers available to do 3 phase, but luckily for us we only had to wait a couple of months. We’ve heard that others have had to wait aContinue reading “Week 74 – Let there be colour! Plus we can officially have electricity!”
Week 73 – More paint spraying, white paint samples..plus go big or go home….!
And so, this week we finished all the undercoat painting, and we used Express Coat by Valspar from B&Q. This one can be used on fresh plaster and doesn’t need watering down, always a bonus! The downstairs took around 4 hours for 110 metre squared which isn’t bad going at all! I do love thisContinue reading “Week 73 – More paint spraying, white paint samples..plus go big or go home….!”
Week 72 – The paint spraying has begun..plus staining wood and another light!
It is so strange to be at a stage where it is down to us and the progress is actually ours to control…mu ha ha! And it is quite simply, based on how proactive or lazy we are feeling on any given week ha! And so this week Andy’s been sanding more of the unfinishedContinue reading “Week 72 – The paint spraying has begun..plus staining wood and another light!”