Week 65 and 66 – Site Progress!

Well week 65 was pretty quiet..just a little bit of woodwork and some insulation upstairs… As you can see, we are pretty much ready to insulate the roof areas, definitely a job for week 67! Plus check out the peacocks, clearly loving the scaffolding at the front ha! And they’re getting braver and braver, evenContinue reading “Week 65 and 66 – Site Progress!”

Week 63 – Site Progress! We have floor insulation..

Oh my goodness..there was a lot of insulation delivered this week! And it was certainly a workout bringing it all into the house in case it rained! And if you live in England you never know when there’s going to be rain regardless of the time of year… And even though it is lightweight, it’sContinue reading “Week 63 – Site Progress! We have floor insulation..”

Week 61 – Site Progress! First fix done plus twinkly lights…

Another milestone this week, the first fix electrics are complete and we can now focus on insulation soon, hopefully week 62! Building control paid site a visit on Wednesday and they are happy with everything so we are good to go when it comes to covering the walls and floors And our very pretty twinklyContinue reading “Week 61 – Site Progress! First fix done plus twinkly lights…”

Week 58 – Site Progress! Plus “fiddly” lights and brick slips..

Lots going on this week! Eddie the electrician has been on site for most of it, finishing off the upstairs wiring and thermostats. The cinema room certainly took some doing…as you can see… Lots of twinkly LEDs to go in here, and doing this now will make the second fix much easier! And next weekContinue reading “Week 58 – Site Progress! Plus “fiddly” lights and brick slips..”

Week 56 – Site Progress..first fix electrics and more stud walls

More progress this week! Andy has been assigned some plumbing tasks and so he made a start on those…cue plumbing related items laid out all pretty in the house ha ha! And he invested in a new drill, and special drill bit making drilling the plumbing holes much easier! Needless to say he’s very happyContinue reading “Week 56 – Site Progress..first fix electrics and more stud walls”

Week 32 – Site Progress!

Well what a week! Much more going on and luckily the weather improved and so the brickwork could continue yay. The front gables are looking so pretty with a lovely brickwork pattern It really looks like a house now that the front gables have been finished! And also the stone cills and name stones arrived…Continue reading “Week 32 – Site Progress!”

Week 30 and 31 – Site Progress!

Not a great deal going on over the Christmas period, aside from a little more roof work on Christmas eve, and then a wait for the last of the bricks so that the gables can be finished Finally arriving in week 30, plus the ogee roof guttering came… And other than that a quiet oneContinue reading “Week 30 and 31 – Site Progress!”

Week 28 and 29 – Site Progress!

Oh the saga of waiting on materials! In this case, bricks. And the difficulty being able to pin people down for dates as well. Hopefully they will be arriving in week 30 so that the gables can be finished fingers crossed! However, at least the central section of the roof trusses have been done, andContinue reading “Week 28 and 29 – Site Progress!”

Underfloor Heating – No brainer!

One of the first (and easiest!) decisions we made about our new home was that we would be having Underfloor heating instead of radiators. As part of the renovation of our last house we installed underfloor heating in the whole ground floor and really liked it, especially Charlie, he loved laying on the warmth! AsContinue reading “Underfloor Heating – No brainer!”