We decided to group the two weeks together as week 26 was a little quiet to say the least. We were waiting until Thursday for the scaffolding to be moved up. Again they kept giving us a date and then not turning up. Obviously we know that all the trades are busy but seriously, whyContinue reading “Week 26 and 27 – Site Progress!”
Tag Archives: renovation
Week 24! (6 months) Site Progress!
Oh my goodness, we are now at the 6 month mark! Andy was so very excited to make the 6 month timelapse. Amazing how much can happen in 6 months and to catch it all on camera as well! This week the brickies were only here at the beginning of the week as there wasn’tContinue reading “Week 24! (6 months) Site Progress!”
Week 22 – Site Progress!
Another week, where does the time go!! Upstairs is really starting to take shape now, it won’t be long before the brickwork has been completed! Block and brickwork at the back of the house, eek! Next up will be the internal block work, I am so excited for that. Need to build myself up toContinue reading “Week 22 – Site Progress!”
Kitchen plans…
Very excited to have a kitchen design on paper,and it looks fabulous! Always a bonus! Originally we were going to go with something super modern, with an industrial twist. Handleless, with Copper and Slate cupboard doors but after lots of consideration we felt that we probably would want to change it in a few years,Continue reading “Kitchen plans…”
Week 21 – Site Progress!
Very busy week on site, lots of brickwork at the front and the sides of the house. There is now just the back to do then onto the internal blockwork upstairs! Andy’s been moving blocks to the scaffolding height every evening and this weekend whilst I’ve given the site a tidy, its already looking likeContinue reading “Week 21 – Site Progress!”
The stairs are ordered!
So excited! It really feels like a big milestone when you are almost ready to have the stairs installed eek. If you haven’t seen our past instagram posts we are going for a precast concrete central staircase. And so the stairs will be made off site and then craned into place We have now signedContinue reading “The stairs are ordered!”
Week 20 – Site Progress!
It was all go on Tuesday this week, the scaffolding guys turned up first thing and moved all the scaffolding up a level so that the brickies can carry on with the rest of the brickwork at first floor level Its a little bit too high now for me! I’m not great with heights soContinue reading “Week 20 – Site Progress!”
Week 19 – Site Progress!
More brickwork this week ready for the scaffolding to be moved up again! The front of the house is really starting to take shape now All very exciting. Plus we have also been making decisions regarding sliding doors (last blog post) and are pretty much ready to order the stairs yay! Looking back at theContinue reading “Week 19 – Site Progress!”
Week 17 – Site Progress!
Well…we were expecting the rest of the scaffolding on Monday so that brickwork could continue however they didn’t turn up until Thursday and so we lost another week of brickwork! But onwards and upwards as they say, blockwork will continue in week 18 up to first floor yay!! And we can now see just howContinue reading “Week 17 – Site Progress!”
Week 11 – Site progress!
The third week of brick laying has entailed the last of the ground floor external bricks at the front of the house, and then blockwork continued! The brickies have also completed our exposed brick wall in the kitchen! Its so strange having a finished internal wall, and its beautiful. We decided to go with theContinue reading “Week 11 – Site progress!”