Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..

Another week and the first fix is just about done…honestly ha! The waste pipes are now in but the plumber is missing a few bits and so hopefully he will be back in week 61…. Plus Harold has been busy with bay window cills and has almost finished the roof tiles too..just ridge tiles toContinue reading “Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..”

Week 46 – Site Progress plus more paint samples…

It’s been pretty quiet for, well pretty much a month or so! My fault of course ha! Just because I wanted stone heads and cills, it has meant that the window fitter couldn’t measure the openings until all the cills were in, and due to all the delays with the scaffolding being moved, it tookContinue reading “Week 46 – Site Progress plus more paint samples…”

We made a concrete sink!

I’m not going to lie….I was pretty excited when it actually worked! Spoiler alert ha! Both myself and Andy love a bit of concrete. It’s so versatile and looks great when textured or smooth. If you haven’t seen our Instagram, our stairs are actually concrete too and we’re going to show it off together withContinue reading “We made a concrete sink!”