Week 87 – We have a kitchen!

Yaassssss! We do indeed have a kitchen and utility! Woop! Andy picked them up on Friday and what a road trip. A 5 hour round trip in total, but it’s all home now and ready for fitting! And definitely one to start in week 88! It’s really filled the back room. I didn’t think we’dContinue reading “Week 87 – We have a kitchen!”

Week 86 – Second fix almost complete plus Crittall samples!

Wow, another milestone…we have light upstairs! And Eddie, the electrician, is almost done! Maybe just a few more days than we are good to go. And the cinema room really is taking shape; these small diamond spotlights are SO twinkly!! And the lightsaber wall lights finish it off a treat! Great advice from Claire atContinue reading “Week 86 – Second fix almost complete plus Crittall samples!”

Week 85 – Tiling DIY! Plus more decision making…

More DIY-ING this week, and this time in the form of tiling! But first, some more decisions with regards to the stairs and, more importantly, the detailing! Having decided to go with a black metal balustrade, we were still a little up in the air as to how it should be fixed to the stairs.Continue reading “Week 85 – Tiling DIY! Plus more decision making…”

Week 73 – More paint spraying, white paint samples..plus go big or go home….!

And so, this week we finished all the undercoat painting, and we used Express Coat by Valspar from B&Q. This one can be used on fresh plaster and doesn’t need watering down, always a bonus! The downstairs took around 4 hours for 110 metre squared which isn’t bad going at all! I do love thisContinue reading “Week 73 – More paint spraying, white paint samples..plus go big or go home….!”

Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..

Another week and the first fix is just about done…honestly ha! The waste pipes are now in but the plumber is missing a few bits and so hopefully he will be back in week 61…. Plus Harold has been busy with bay window cills and has almost finished the roof tiles too..just ridge tiles toContinue reading “Week 60 – Site Progress! First fix is almost finished plus window cills and using the bifolds..”

Week 46 – Site Progress plus more paint samples…

It’s been pretty quiet for, well pretty much a month or so! My fault of course ha! Just because I wanted stone heads and cills, it has meant that the window fitter couldn’t measure the openings until all the cills were in, and due to all the delays with the scaffolding being moved, it tookContinue reading “Week 46 – Site Progress plus more paint samples…”

We made a concrete sink!

I’m not going to lie….I was pretty excited when it actually worked! Spoiler alert ha! Both myself and Andy love a bit of concrete. It’s so versatile and looks great when textured or smooth. If you haven’t seen our Instagram, our stairs are actually concrete too and we’re going to show it off together withContinue reading “We made a concrete sink!”