Week 33 – Site Progress!

Well it’s been a busy week! The gables are now finished and the chimney isn’t far off plus the roofers have felted the roof now so at least the house is covered if we have any rain yay! Annddddd the name stones are in…. So so pleased with them! Such a lovely personal touch toContinue reading “Week 33 – Site Progress!”

Week 30 and 31 – Site Progress!

Not a great deal going on over the Christmas period, aside from a little more roof work on Christmas eve, and then a wait for the last of the bricks so that the gables can be finished Finally arriving in week 30, plus the ogee roof guttering came… And other than that a quiet oneContinue reading “Week 30 and 31 – Site Progress!”

Week 28 and 29 – Site Progress!

Oh the saga of waiting on materials! In this case, bricks. And the difficulty being able to pin people down for dates as well. Hopefully they will be arriving in week 30 so that the gables can be finished fingers crossed! However, at least the central section of the roof trusses have been done, andContinue reading “Week 28 and 29 – Site Progress!”

Week 26 and 27 – Site Progress!

We decided to group the two weeks together as week 26 was a little quiet to say the least. We were waiting until Thursday for the scaffolding to be moved up. Again they kept giving us a date and then not turning up. Obviously we know that all the trades are busy but seriously, whyContinue reading “Week 26 and 27 – Site Progress!”

Glass decided…finally!

About time! We were so undecided for awhile as you may have noticed on instagram. Simply because, originally, before we’d given it a lot of thought, we were sold on aluminium. I really liked the slim lines and athestics. And we had decided that if they weren’t crazy expensive they would be our go toContinue reading “Glass decided…finally!”

Week 24! (6 months) Site Progress!

Oh my goodness, we are now at the 6 month mark! Andy was so very excited to make the 6 month timelapse. Amazing how much can happen in 6 months and to catch it all on camera as well! This week the brickies were only here at the beginning of the week as there wasn’tContinue reading “Week 24! (6 months) Site Progress!”

Week 22 – Site Progress!

Another week, where does the time go!! Upstairs is really starting to take shape now, it won’t be long before the brickwork has been completed! Block and brickwork at the back of the house, eek! Next up will be the internal block work, I am so excited for that. Need to build myself up toContinue reading “Week 22 – Site Progress!”

Week 21 – Site Progress!

Very busy week on site, lots of brickwork at the front and the sides of the house. There is now just the back to do then onto the internal blockwork upstairs! Andy’s been moving blocks to the scaffolding height every evening and this weekend whilst I’ve given the site a tidy, its already looking likeContinue reading “Week 21 – Site Progress!”

Week 20 – Site Progress!

It was all go on Tuesday this week, the scaffolding guys turned up first thing and moved all the scaffolding up a level so that the brickies can carry on with the rest of the brickwork at first floor level Its a little bit too high now for me! I’m not great with heights soContinue reading “Week 20 – Site Progress!”

Week 19 – Site Progress!

More brickwork this week ready for the scaffolding to be moved up again! The front of the house is really starting to take shape now All very exciting. Plus we have also been making decisions regarding sliding doors (last blog post) and are pretty much ready to order the stairs yay! Looking back at theContinue reading “Week 19 – Site Progress!”