Week 48 – Site Progress! We have windows AND bifolds!

What an exciting milestone this week! After a ten week wait, the windows arrived yay. As you can imagine, we were very excited. And all of them are in now, with the exception of the bay windows..it will be week 49 for those and then the tiling can begin We are so very close toContinue reading “Week 48 – Site Progress! We have windows AND bifolds!”

Week 39 and 40 – Site Progress!

Not a whole lot to report, simply because the windows and doors won’t be arriving for another month or so, which means there is no rush really! The garage roof trusses are up, and we ordered our garage door too eek! I didn’t realise I’d get excited over a garage door…and I don’t think AndyContinue reading “Week 39 and 40 – Site Progress!”

Week 36 – Site Progress!

We have solar panels! And just in time before the scaffolding comes down next week…. To pass the SAP assessment (something all new houses have to meet) we needed to have solar panels, the financial incentives for having solar aren’t what they used to be but our electric bill should go down from around £60Continue reading “Week 36 – Site Progress!”

Week 32 – Site Progress!

Well what a week! Much more going on and luckily the weather improved and so the brickwork could continue yay. The front gables are looking so pretty with a lovely brickwork pattern It really looks like a house now that the front gables have been finished! And also the stone cills and name stones arrived…Continue reading “Week 32 – Site Progress!”

Week 24! (6 months) Site Progress!

Oh my goodness, we are now at the 6 month mark! Andy was so very excited to make the 6 month timelapse. Amazing how much can happen in 6 months and to catch it all on camera as well! This week the brickies were only here at the beginning of the week as there wasn’tContinue reading “Week 24! (6 months) Site Progress!”

Week 17 – Site Progress!

Well…we were expecting the rest of the scaffolding on Monday so that brickwork could continue however they didn’t turn up until Thursday and so we lost another week of brickwork! But onwards and upwards as they say, blockwork will continue in week 18 up to first floor yay!! And we can now see just howContinue reading “Week 17 – Site Progress!”

Week 16 – Site Progress!

Well..what can I say..it has been a VERY quiet week on site! We have been waiting for scaffolding alllllllll week, and so the brickies haven’t been able to continue to first floor. Very frustrating. Added to the fact that we kept being told that they were coming. Oh well! It came on Friday and needlessContinue reading “Week 16 – Site Progress!”

Week 14 – Site Progress!

Another busy week apart from some rain…standard British weather! We now have steel though eek! Very exciting. Check out the mechanism to put the steel in place! That looked like it really took some leverage and energy! Plus a wood delivery! Lots of joists are in place now…check out our view from the current house…Continue reading “Week 14 – Site Progress!”

Giveaway Alert!

We are blown away by the renders @envisionhomedesigns have very kindly gifted to us, using our 2D plans. Sunset render above…love! https://www.instagram.com/envisionhomedesigns/ Such a fabulous way to really visualise your project! And so lifelike! If you would like to be in with a chance to win the same front façade for your project check outContinue reading “Giveaway Alert!”

Week 13 – Site progress!

More blockwork this week with internal walls and actual doorways! Eek! Plus the fireplace has been finished as well, and it is beautiful. As we have no doubt mentioned numerous times! We are leaving it exactly like this, no painting of the concrete lintel. It looks so good as is! Plus the peacocks decided toContinue reading “Week 13 – Site progress!”